testtest

Building a Rifle Range

I've been building a 700yrd rifle range behind my house. I'm using old galvanized guardrail I beams welded into a T then sank into the ground for mast's to hang plywood backed paper targets or AR500 steel targets. I sank a steel mast every 100yrds starting at 100yrd from the bench out to 500. Eventually I will sink another mast at 600 and another at 700. I will have the ability to switch up different size targets at different ranges for different levels of difficulty. At least that's the idea! IMG_20220423_163150546_HDR.jpg
The bottom picture would be looking down range from the bench. The logging road (witch dead ends) makes it easy to check, switch and swap out targets.IMG_20220423_164605340_HDR.jpg
 
I've been building a 700yrd rifle range behind my house. I'm using old galvanized guardrail I beams welded into a T then sank into the ground for mast's to hang plywood backed paper targets or AR500 steel targets. I sank a steel mast every 100yrds starting at 100yrd from the bench out to 500. Eventually I will sink another mast at 600 and another at 700. I will have the ability to switch up different size targets at different ranges for different levels of difficulty. At least that's the idea! View attachment 26730
The bottom picture would be looking down range from the bench. The logging road (witch dead ends) makes it easy to check, switch and swap out targets.View attachment 26731
Wish I had that kind of land brother. Very nice.
 
Are you beating those risers into the ground with an excavator bucket, sledge hammer, or other? Lotta big rocks in the unconsolidated soil up around you. Wouldn't be surprised if you had to re-locate your post locations multiple times to avoid boulders. The granite boulders you guys have are pretty hard...
 
Are you beating those risers into the ground with an excavator bucket, sledge hammer, or other? Lotta big rocks in the unconsolidated soil up around you. Wouldn't be surprised if you had to re-locate your post locations multiple times to avoid boulders. The granite boulders you guys have are pretty hard...
Wasn't to bad. I only had to relocate one of five. There is a pretty good layer of overburden in that area. About three feet until I started hitting rocks. The holes were easily dug with a Post Hole Digger. I have a PHD in digging holes! 😂 The hardest part was packing the T posts on my shoulder from the road to their locations. A lot of sweating and curssing was involved! 😂
 
Wasn't to bad. I only had to relocate one of five. There is a pretty good layer of overburden in that area. About three feet until I started hitting rocks. The holes were easily dug with a Post Hole Digger. I have a PHD in digging holes! 😂 The hardest part was packing the T posts on my shoulder from the road to their locations. A lot of sweating and curssing was involved! 😂
I'd rate that as a case of beer job!
 
Wasn't to bad. I only had to relocate one of five. There is a pretty good layer of overburden in that area. About three feet until I started hitting rocks. The holes were easily dug with a Post Hole Digger. I have a PHD in digging holes! 😂 The hardest part was packing the T posts on my shoulder from the road to their locations. A lot of sweating and curssing was involved! 😂
We are paisan then Cowboy. I am a hole digging mofo. Point of fact, Bassbob actually digs holes for a living. And trenches.
 
2600' of trench for 8" gas main, now under the new soccer stadium in downtown STL.
OEZ3MZ3.jpg



Had to tie in to 12" steel with a bottom outlet.
uSAQcKN.jpg


QGttR6M.jpg


Z4xNe7B.jpg


Welders are always a pain in the ass. You can't just dig and shore a hole so they can safely weld and you can tap the main, you need to make them comfortable. You can see Ian back there laying down on the job.
WHdCndx.jpg


When rain or ground water fills your trench overnight you gotta spend a few hours pumping it out. Thankfully I stacked the main ( basically dropped piles of 1" minus every 25 feet or so) so it wasn't floating when we got in the next day.
yTPQ8wF.jpg


M2MZF0A.jpg


After digging the trench, in this case about 40" deep, fusing together 50' sticks of 8" and dropping them, hole gets backfilled with minus and tamped with a hydraulic tamper in 1" lifts. This was a major construction sight with excavators and earth movers the size of buildings rolling around so the trench had to be fairly deep and properly backfilled and tamped. The bad thing was that we already knew there was going to be a 4' fill in the middle 1000' of trench and another building, which would need a service, was going to be erected. That meant to dig this main up to install the service for that building eventually, someone was going to have to dig 7' down to get the main. Then shore the hole. Basically about 2 days of prep work to run a service that might take a couple hours to install. And sure enough about 11 months later I got a call from a guy tasked with running this service asking me how deep the main was. :)

M2MZF0A.jpg



4DlYZaK.jpg



uZizz5x.jpg



The location of this new ballpark was partially where an onramp to highway 40 sat. Many, many years ago city blocks were leveled and 40' of fill was brought in to build the on ramp. When I first went to look at the job the site was still 40' taller than what it would be when I showed up to start digging a week and half later. That gives you an idea of how large these excavators were that they could move that much dirt that quickly. So at the grade I was digging I was pretty much trenching through foundations, old abandoned gas and water services and rubble that had been buried 40' deep for half a century or more. This meant 2 things. Since digging the trench was going to entail digging out all the type of hard rubble and metal fill that you cannot put plastic gas mains on, I was going to have to dig all that crap out. Meaning tracking back over my ditch was going to be impossible. So I had to make damn sure I had depth and a clean ditch before I moved down the line. It also meant that I was going to have to backfill it and tamp it in in 50 or 100 foot increments. I still managed to get about 350-400 feet a day. That's dug, pipe dropped and backfilled. 12 hour days, 6 days a week. Everything over 8 hours was time and a half and I got paid a premium for it being a haz mat area the entire time I was there. I did very well those 2 months. This job was very much a timed deal. In order for STL to be granted a franchise by MLS this stadium had to be done by a certain date. When I dug across 24th street, which is where the FBI building is located, I had some FBI guys come and yell at me for blocking their little short cut to the gas station. I told them in no uncertain terms that they could either drive around the block or eff off, either one worked for me. A bigshot at the company got a call from the FBI complaining about me. In the one thing since I started here that made me proud of the company, the FBI was told that if they wanted to explain to those billionaires why STL wouldn't be getting a soccer team that was on them, otherwise they could pound sand. I never heard from them FBI guys again.

83mzQPn.jpg


A tie in hole in the making. My tie-ins incidentally are works of art. :)

5pVQCgr.jpg



I spent a few years digging holes like this too. These are holes over service tees which we abandon when they slate a building for demolition, which in north St. Louis there is endless work of that nature. This was after abandoning the services to two houses and backfilling with the rubble. A paving crew will come along later and dig out the tops and fill it with 12" of concrete.

vrZV3TO.jpg


Here are 6 holes I dug at my house. They are 48" deep, belled out like an elephant foot at the bottom, big enough for 10" sonotube. Which I dug by hand. Then hand mixed 87 bags ( 80LBS) of concrete. Set my beams and set my building well up above the highest known flood level. This is currently my humble little shop.

BiNdZbH.jpg


ZRhdZhb.jpg


LNNWmYE.jpg


s9DG31W.jpg


fKQaTvK.jpg


PmRpf8Q.jpg


hCdOAGy.jpg



Anyway, even though the majority of these are pictures of holes I dug in an excavator, a huge part of my job involves hand digging through rubble. I dig over gaslines and other utilities with an excavator every day and once I feel what I am looking for with my bucket it's time to jump out and grab a shovel.
 
2600' of trench for 8" gas main, now under the new soccer stadium in downtown STL.
OEZ3MZ3.jpg



Had to tie in to 12" steel with a bottom outlet.
uSAQcKN.jpg


QGttR6M.jpg


Z4xNe7B.jpg


Welders are always a pain in the ass. You can't just dig and shore a hole so they can safely weld and you can tap the main, you need to make them comfortable. You can see Ian back there laying down on the job.
WHdCndx.jpg


When rain or ground water fills your trench overnight you gotta spend a few hours pumping it out. Thankfully I stacked the main ( basically dropped piles of 1" minus every 25 feet or so) so it wasn't floating when we got in the next day.
yTPQ8wF.jpg


M2MZF0A.jpg


After digging the trench, in this case about 40" deep, fusing together 50' sticks of 8" and dropping them, hole gets backfilled with minus and tamped with a hydraulic tamper in 1" lifts. This was a major construction sight with excavators and earth movers the size of buildings rolling around so the trench had to be fairly deep and properly backfilled and tamped. The bad thing was that we already knew there was going to be a 4' fill in the middle 1000' of trench and another building, which would need a service, was going to be erected. That meant to dig this main up to install the service for that building eventually, someone was going to have to dig 7' down to get the main. Then shore the hole. Basically about 2 days of prep work to run a service that might take a couple hours to install. And sure enough about 11 months later I got a call from a guy tasked with running this service asking me how deep the main was. :)

M2MZF0A.jpg



4DlYZaK.jpg



uZizz5x.jpg



The location of this new ballpark was partially where an onramp to highway 40 sat. Many, many years ago city blocks were leveled and 40' of fill was brought in to build the on ramp. When I first went to look at the job the site was still 40' taller than what it would be when I showed up to start digging a week and half later. That gives you an idea of how large these excavators were that they could move that much dirt that quickly. So at the grade I was digging I was pretty much trenching through foundations, old abandoned gas and water services and rubble that had been buried 40' deep for half a century or more. This meant 2 things. Since digging the trench was going to entail digging out all the type of hard rubble and metal fill that you cannot put plastic gas mains on, I was going to have to dig all that crap out. Meaning tracking back over my ditch was going to be impossible. So I had to make damn sure I had depth and a clean ditch before I moved down the line. It also meant that I was going to have to backfill it and tamp it in in 50 or 100 foot increments. I still managed to get about 350-400 feet a day. That's dug, pipe dropped and backfilled. 12 hour days, 6 days a week. Everything over 8 hours was time and a half and I got paid a premium for it being a haz mat area the entire time I was there. I did very well those 2 months. This job was very much a timed deal. In order for STL to be granted a franchise by MLS this stadium had to be done by a certain date. When I dug across 24th street, which is where the FBI building is located, I had some FBI guys come and yell at me for blocking their little short cut to the gas station. I told them in no uncertain terms that they could either drive around the block or eff off, either one worked for me. A bigshot at the company got a call from the FBI complaining about me. In the one thing since I started here that made me proud of the company, the FBI was told that if they wanted to explain to those billionaires why STL wouldn't be getting a soccer team that was on them, otherwise they could pound sand. I never heard from them FBI guys again.

83mzQPn.jpg


A tie in hole in the making. My tie-ins incidentally are works of art. :)

5pVQCgr.jpg



I spent a few years digging holes like this too. These are holes over service tees which we abandon when they slate a building for demolition, which in north St. Louis there is endless work of that nature. This was after abandoning the services to two houses and backfilling with the rubble. A paving crew will come along later and dig out the tops and fill it with 12" of concrete.

vrZV3TO.jpg


Here are 6 holes I dug at my house. They are 48" deep, belled out like an elephant foot at the bottom, big enough for 10" sonotube. Which I dug by hand. Then hand mixed 87 bags ( 80LBS) of concrete. Set my beams and set my building well up above the highest known flood level. This is currently my humble little shop.

BiNdZbH.jpg


ZRhdZhb.jpg


LNNWmYE.jpg


s9DG31W.jpg


fKQaTvK.jpg


PmRpf8Q.jpg


hCdOAGy.jpg



Anyway, even though the majority of these are pictures of holes I dug in an excavator, a huge part of my job involves hand digging through rubble. I dig over gaslines and other utilities with an excavator every day and once I feel what I am looking for with my bucket it's time to jump out and grab a shovel.
Absolutely Impressive!!! All of it! And that "humble little shop" is bad a**! That foundation looks skook'em to say the least!👍
 
Last edited:
I call on water well contractors and septic installers...they dig every day using the same type of equipment, just on a much smaller scale...nice pics. Every one of them has a live gas and/or electric service line in their days...diggers' hotline is not always spot-on accurate! Good to see you using trench boxes. Most of my guys do not (even though Osha says they have to). I know you have to with the type of work you do.
 
I call on water well contractors and septic installers...they dig every day using the same type of equipment, just on a much smaller scale...nice pics. Every one of them has a live gas and/or electric service line in their days...diggers' hotline is not always spot-on accurate! Good to see you using trench boxes. Most of my guys do not (even though Osha says they have to). I know you have to with the type of work you do.
Not always spot on is being very generous. It’s fair to say that USIC is almost always way off. I locate communication, gas and water lines with my own locator just to be safe. I never complain about USIC though because as long as they’re 2’ or more off they are responsible for damage. Although in 10 plus years here digging over utilities I have never hit anything, knock on wood.
 
2600' of trench for 8" gas main, now under the new soccer stadium in downtown STL.
OEZ3MZ3.jpg



Had to tie in to 12" steel with a bottom outlet.
uSAQcKN.jpg


QGttR6M.jpg


Z4xNe7B.jpg


Welders are always a pain in the ass. You can't just dig and shore a hole so they can safely weld and you can tap the main, you need to make them comfortable. You can see Ian back there laying down on the job.
WHdCndx.jpg


When rain or ground water fills your trench overnight you gotta spend a few hours pumping it out. Thankfully I stacked the main ( basically dropped piles of 1" minus every 25 feet or so) so it wasn't floating when we got in the next day.
yTPQ8wF.jpg


M2MZF0A.jpg


After digging the trench, in this case about 40" deep, fusing together 50' sticks of 8" and dropping them, hole gets backfilled with minus and tamped with a hydraulic tamper in 1" lifts. This was a major construction sight with excavators and earth movers the size of buildings rolling around so the trench had to be fairly deep and properly backfilled and tamped. The bad thing was that we already knew there was going to be a 4' fill in the middle 1000' of trench and another building, which would need a service, was going to be erected. That meant to dig this main up to install the service for that building eventually, someone was going to have to dig 7' down to get the main. Then shore the hole. Basically about 2 days of prep work to run a service that might take a couple hours to install. And sure enough about 11 months later I got a call from a guy tasked with running this service asking me how deep the main was. :)

M2MZF0A.jpg



4DlYZaK.jpg



uZizz5x.jpg



The location of this new ballpark was partially where an onramp to highway 40 sat. Many, many years ago city blocks were leveled and 40' of fill was brought in to build the on ramp. When I first went to look at the job the site was still 40' taller than what it would be when I showed up to start digging a week and half later. That gives you an idea of how large these excavators were that they could move that much dirt that quickly. So at the grade I was digging I was pretty much trenching through foundations, old abandoned gas and water services and rubble that had been buried 40' deep for half a century or more. This meant 2 things. Since digging the trench was going to entail digging out all the type of hard rubble and metal fill that you cannot put plastic gas mains on, I was going to have to dig all that crap out. Meaning tracking back over my ditch was going to be impossible. So I had to make damn sure I had depth and a clean ditch before I moved down the line. It also meant that I was going to have to backfill it and tamp it in in 50 or 100 foot increments. I still managed to get about 350-400 feet a day. That's dug, pipe dropped and backfilled. 12 hour days, 6 days a week. Everything over 8 hours was time and a half and I got paid a premium for it being a haz mat area the entire time I was there. I did very well those 2 months. This job was very much a timed deal. In order for STL to be granted a franchise by MLS this stadium had to be done by a certain date. When I dug across 24th street, which is where the FBI building is located, I had some FBI guys come and yell at me for blocking their little short cut to the gas station. I told them in no uncertain terms that they could either drive around the block or eff off, either one worked for me. A bigshot at the company got a call from the FBI complaining about me. In the one thing since I started here that made me proud of the company, the FBI was told that if they wanted to explain to those billionaires why STL wouldn't be getting a soccer team that was on them, otherwise they could pound sand. I never heard from them FBI guys again.

83mzQPn.jpg


A tie in hole in the making. My tie-ins incidentally are works of art. :)

5pVQCgr.jpg



I spent a few years digging holes like this too. These are holes over service tees which we abandon when they slate a building for demolition, which in north St. Louis there is endless work of that nature. This was after abandoning the services to two houses and backfilling with the rubble. A paving crew will come along later and dig out the tops and fill it with 12" of concrete.

vrZV3TO.jpg


Here are 6 holes I dug at my house. They are 48" deep, belled out like an elephant foot at the bottom, big enough for 10" sonotube. Which I dug by hand. Then hand mixed 87 bags ( 80LBS) of concrete. Set my beams and set my building well up above the highest known flood level. This is currently my humble little shop.

BiNdZbH.jpg


ZRhdZhb.jpg


LNNWmYE.jpg


s9DG31W.jpg


fKQaTvK.jpg


PmRpf8Q.jpg


hCdOAGy.jpg



Anyway, even though the majority of these are pictures of holes I dug in an excavator, a huge part of my job involves hand digging through rubble. I dig over gaslines and other utilities with an excavator every day and once I feel what I am looking for with my bucket it's time to jump out and grab a shovel.
Bassbob, what a skill set! You are certainly very talented at work and at home. It appears you work in some harsh conditions, and I tip my hat to you for the job you do on a daily basis!
 
Bassbob, what a skill set! You are certainly a very talented at work and at home. It appears you work in some harsh conditions, and I tip my hat to you for the job you do on a daily basis!
😂😂😂 I thought you were talking about my rifle range when you said "I'm really impressed" 😂😂😂 Sorry to be so vein, and yes I agree. Looks like BBob knows his s**t when it comes to trenching and large scale industrial plumbing jobs for sure! I'm definitely impressed!
 
Back
Top